If you’re considering a leased line for your business, here’s an overview of the order steps and average lead times:
- KM1 – Order Acknowledged: 5 days
- KM2 – Order Placed with Supplier: 5 days
- KM3 – Order Verified and Accepted by Supplier: 13 days
- KM4 – Site Access Request (Survey): 14 days
- KM5 – No ECCs Confirmation / ECCs Confirmation (Excess Construction Costs
- KM6 – Estimated Delivery Date: 13 days
- KM7 – Site Access Request (On-site Works): 12 days
- KM8 – Site Access Request (Fit and Test): 16 days
- KM9 – Pre-Configured Router Shipment
- KM10 – Circuit Ready to Bring Live: 5 days
- KM11 – Service Handover: 5 days